{"article":{"id":1826,"slug":"aizo-group-secures-rm346-million-islamic-financing-for-100-mw-floating-solar-plant-in-perak","title":"Aizo Group Secures RM346 Million Islamic Financing for 100 MW Floating Solar Plant in Perak","category":"news","summary":"AIZO Group secures RM346 million Islamic financing from Bank Pembangunan Malaysia for a 99.99 MWac floating solar plant in Kampar, Perak, targeting mid-2028 completion.","content":"## English\n\n* **AIZO Group Berhad's subsidiary Wawasan Demi Sdn Bhd** executed Islamic financing agreements with Bank Pembangunan Malaysia Berhad (BPMB) on 18 June 2026\n* **Total financing: RM346.19 million** for a Large-Scale Solar Photovoltaic (LSSPV) plant in Kampar, Perak\n* **Tawarruq Asset Financing (TWA)**: Up to RM256 million covering 80% of engineering, procurement, construction and commissioning (EPCC) costs\n* **Bank Guarantee-i**: Up to RM89.99 million as performance guarantee for TNB delay payment, plus RM200,000 for SSP works to TNB\n* **Repayment period: Up to 19 years** from first utilisation of the Tawarruq facility\n* **Project capacity: 99.99 MWac floating solar** — one of Malaysia's largest floating solar installations\n* **Land collateral**: 11 leasehold land parcels totalling approximately 177 hectares in Kampar, Perak\n* **Project completion target: Mid-2028**\n* **Corporate restructuring approved**: Bursa Malaysia (17 April 2026) and shareholders (29 May 2026) approved private placement, share capital reduction, and rights issue with free detachable warrants\n* **Malaysia's LSS pipeline** continues to expand as Islamic financing structures make large-scale solar projects more accessible to domestic developers\n\n## 中文\n\n* **AIZO集团子公司Wawasan Demi私人有限公司**于2026年6月18日与马来西亚发展银行（BPMB）签署伊斯兰融资协议\n* **总融资额3.4619亿令吉**，用于霹雳州金宝的大型太阳能光伏（LSSPV）电站\n* **Tawarruq资产融资（TWA）**：最高2.56亿令吉，覆盖工程、采购、施工和调试（EPCC）成本的80%\n* **银行担保-i**：最高8,999万令吉作为TNB延迟付款的履约担保，另加20万令吉用于TNB的SSP工程履约担保\n* **还款期限：自首次动用Tawarruq设施起最长19年**\n* **项目容量：99.99兆瓦交流浮动太阳能**——马来西亚最大的浮动太阳能装置之一\n* **土地抵押**：霹雳州金宝的11块租赁地，总面积约177公顷\n* **项目完工目标：2028年年中**\n* **企业重组获批**：马来西亚交易所（2026年4月17日）和股东（2026年5月29日）批准了私募配售、股本削减和附带免费分离认股权证的配股\n* **马来西亚大型太阳能项目管线**持续扩张，伊斯兰融资结构使大型太阳能项目对本土开发商更具可及性","html_content":"<h2>English</h2>\n<ul>\n<li><strong>AIZO Group Berhad&#39;s subsidiary Wawasan Demi Sdn Bhd</strong> executed Islamic financing agreements with Bank Pembangunan Malaysia Berhad (BPMB) on 18 June 2026</li>\n<li><strong>Total financing: RM346.19 million</strong> for a Large-Scale Solar Photovoltaic (LSSPV) plant in Kampar, Perak</li>\n<li><strong>Tawarruq Asset Financing (TWA)</strong>: Up to RM256 million covering 80% of engineering, procurement, construction and commissioning (EPCC) costs</li>\n<li><strong>Bank Guarantee-i</strong>: Up to RM89.99 million as performance guarantee for TNB delay payment, plus RM200,000 for SSP works to TNB</li>\n<li><strong>Repayment period: Up to 19 years</strong> from first utilisation of the Tawarruq facility</li>\n<li><strong>Project capacity: 99.99 MWac floating solar</strong> — one of Malaysia&#39;s largest floating solar installations</li>\n<li><strong>Land collateral</strong>: 11 leasehold land parcels totalling approximately 177 hectares in Kampar, Perak</li>\n<li><strong>Project completion target: Mid-2028</strong></li>\n<li><strong>Corporate restructuring approved</strong>: Bursa Malaysia (17 April 2026) and shareholders (29 May 2026) approved private placement, share capital reduction, and rights issue with free detachable warrants</li>\n<li><strong>Malaysia&#39;s LSS pipeline</strong> continues to expand as Islamic financing structures make large-scale solar projects more accessible to domestic developers</li>\n</ul>\n<h2>中文</h2>\n<ul>\n<li><strong>AIZO集团子公司Wawasan Demi私人有限公司</strong>于2026年6月18日与马来西亚发展银行（BPMB）签署伊斯兰融资协议</li>\n<li><strong>总融资额3.4619亿令吉</strong>，用于霹雳州金宝的大型太阳能光伏（LSSPV）电站</li>\n<li><strong>Tawarruq资产融资（TWA）</strong>：最高2.56亿令吉，覆盖工程、采购、施工和调试（EPCC）成本的80%</li>\n<li><strong>银行担保-i</strong>：最高8,999万令吉作为TNB延迟付款的履约担保，另加20万令吉用于TNB的SSP工程履约担保</li>\n<li><strong>还款期限：自首次动用Tawarruq设施起最长19年</strong></li>\n<li><strong>项目容量：99.99兆瓦交流浮动太阳能</strong>——马来西亚最大的浮动太阳能装置之一</li>\n<li><strong>土地抵押</strong>：霹雳州金宝的11块租赁地，总面积约177公顷</li>\n<li><strong>项目完工目标：2028年年中</strong></li>\n<li><strong>企业重组获批</strong>：马来西亚交易所（2026年4月17日）和股东（2026年5月29日）批准了私募配售、股本削减和附带免费分离认股权证的配股</li>\n<li><strong>马来西亚大型太阳能项目管线</strong>持续扩张，伊斯兰融资结构使大型太阳能项目对本土开发商更具可及性</li>\n</ul>\n","author":"Eternalgy Market Intelligence Team","tags":"solar, malaysia, market","meta_description":"AIZO Group secures RM346M Islamic financing for 100 MW floating solar plant in Perak, Malaysia's expanding LSS pipeline with 19-year repayment structure.","published":true,"created_at":"2026-06-18T11:57:32.000Z","updated_at":"2026-06-18T21:13:28.331Z","source_url":"https://www.nst.com.my/business/corporate/2026/06/1466657/aizos-unit-secures-rm34619mil-islamic-financing-facilities","source_name":"NST Online","published_at":"2026-06-18T11:57:32.000Z","noindex":false,"marketing_line":"Eternalgy is your trusted solar PV EPC in Malaysia — CIDB G3 & SEDA RPVI certified. Go solar today: https://eternalgy.me/aizo-group-secures-rm346-million-islamic-financing-for-100-mw-floating-solar-plant-in-perak","marketing_line_cn":"Eternalgy是您值得信赖的马来西亚太阳能光伏EPC——持有CIDB G3和SEDA RPVI认证。立即选择太阳能：https://eternalgy.me/aizo-group-secures-rm346-million-islamic-financing-for-100-mw-floating-solar-plant-in-perak"},"schemaData":{"@context":"https://schema.org","@graph":[{"@type":"NewsArticle","@id":"https://eternalgy.me/aizo-group-secures-rm346-million-islamic-financing-for-100-mw-floating-solar-plant-in-perak#newsarticle","headline":"Aizo Group Secures RM346 Million Islamic Financing for 100 MW Floating Solar Plant in Perak","description":"AIZO Group secures RM346 million Islamic financing from Bank Pembangunan Malaysia for a 99.99 MWac floating solar plant in Kampar, Perak, targeting mid-2028 completion.","image":["https://eternalgy.me/logo.png"],"datePublished":"2026-06-18T11:57:32.000Z","dateModified":"2026-06-18T21:13:28.331Z","author":{"@type":"Person","name":"Eternalgy Market Intelligence Team"},"publisher":{"@type":"Organization","name":"Eternalgy Sdn Bhd","url":"https://eternalgy.me","logo":{"@type":"ImageObject","url":"https://eternalgy.me/logo.png"},"foundingDate":"2023-09-15","sameAs":["https://eternalgy.com","https://solarpanels.my","https://solarpanels.onesync.my","https://solar100.com.my"]},"mainEntityOfPage":"https://eternalgy.me/aizo-group-secures-rm346-million-islamic-financing-for-100-mw-floating-solar-plant-in-perak","isBasedOn":"https://www.nst.com.my/business/corporate/2026/06/1466657/aizos-unit-secures-rm34619mil-islamic-financing-facilities"},{"@type":"BreadcrumbList","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https://eternalgy.me"},{"@type":"ListItem","position":2,"name":"Energy News","item":"https://eternalgy.me/news"},{"@type":"ListItem","position":3,"name":"Aizo Group Secures RM346 Million Islamic Financing for 100 MW Floating Solar Plant in Perak","item":"https://eternalgy.me/aizo-group-secures-rm346-million-islamic-financing-for-100-mw-floating-solar-plant-in-perak"}]}]}}