English

  • Project Overview: TotalEnergies and MK Land Holdings Berhad are partnering to build a 30 MWac (50 MWp) solar plant in Kedah, Malaysia.
  • Timeline & Investment: Construction is scheduled to begin in Q3 2027 with a total investment of RM 145 million (US$ 37 million).
  • Technical Specifications: The facility will feature approximately 80,000 photovoltaic panels covering 115 acres, including a new 132 kV substation to boost grid interconnection.
  • Power Purchase Agreements: The plant will generate an estimated 1.5 TWh of electricity over its lifespan, sold via 21-year PPAs to data centers and industrial clients.
  • Regulatory Background: The project was secured under the Malaysian Corporate Green Power Programme (CGPP) in August 2023, with financing provided by BNP Paribas Malaysia Berhad.

中文

  • 项目概览:道达尔能源(TotalEnergies)与马来西亚 MK Land Holdings Berhad 合作,在马来西亚吉打州建设一座 30 MWac (50 MWp) 的太阳能发电厂。
  • 时间表与投资:项目计划于 2027 年第三季度动工,总投资额为 1.45 亿林吉特(约 3700 万美元)。
  • 技术规格:该设施将配备约 8 万块光伏板,占地 115 英亩,并新建一座 132 kV 变电站以加强电网互联。
  • 购电协议:该电厂预计在生命周期内产生 1.5 TWh 电力,将通过 21 年的长期购电协议(PPA)供应给数据中心及工业客户。
  • 政策背景:该项目于 2023 年 8 月通过马来西亚企业绿色电力计划(CGPP)获批,融资由法国巴黎银行马来西亚分行(BNP Paribas Malaysia Berhad)安排。