Aizo Group Secures RM346 Million Islamic Financing for 100 MW Floating Solar Plant in Perak
English
- AIZO Group Berhad's subsidiary Wawasan Demi Sdn Bhd executed Islamic financing agreements with Bank Pembangunan Malaysia Berhad (BPMB) on 18 June 2026
- Total financing: RM346.19 million for a Large-Scale Solar Photovoltaic (LSSPV) plant in Kampar, Perak
- Tawarruq Asset Financing (TWA): Up to RM256 million covering 80% of engineering, procurement, construction and commissioning (EPCC) costs
- Bank Guarantee-i: Up to RM89.99 million as performance guarantee for TNB delay payment, plus RM200,000 for SSP works to TNB
- Repayment period: Up to 19 years from first utilisation of the Tawarruq facility
- Project capacity: 99.99 MWac floating solar — one of Malaysia's largest floating solar installations
- Land collateral: 11 leasehold land parcels totalling approximately 177 hectares in Kampar, Perak
- Project completion target: Mid-2028
- Corporate restructuring approved: Bursa Malaysia (17 April 2026) and shareholders (29 May 2026) approved private placement, share capital reduction, and rights issue with free detachable warrants
- Malaysia's LSS pipeline continues to expand as Islamic financing structures make large-scale solar projects more accessible to domestic developers
中文
- AIZO集团子公司Wawasan Demi私人有限公司于2026年6月18日与马来西亚发展银行(BPMB)签署伊斯兰融资协议
- 总融资额3.4619亿令吉,用于霹雳州金宝的大型太阳能光伏(LSSPV)电站
- Tawarruq资产融资(TWA):最高2.56亿令吉,覆盖工程、采购、施工和调试(EPCC)成本的80%
- 银行担保-i:最高8,999万令吉作为TNB延迟付款的履约担保,另加20万令吉用于TNB的SSP工程履约担保
- 还款期限:自首次动用Tawarruq设施起最长19年
- 项目容量:99.99兆瓦交流浮动太阳能——马来西亚最大的浮动太阳能装置之一
- 土地抵押:霹雳州金宝的11块租赁地,总面积约177公顷
- 项目完工目标:2028年年中
- 企业重组获批:马来西亚交易所(2026年4月17日)和股东(2026年5月29日)批准了私募配售、股本削减和附带免费分离认股权证的配股
- 马来西亚大型太阳能项目管线持续扩张,伊斯兰融资结构使大型太阳能项目对本土开发商更具可及性